AI overviewA £20bn partnership between Drax, Brookfield and Radiant aims to develop an AI datacentre at the Drax site in North Yorkshire, with capacity eventually exceeding 1GW. In its first phase, expected to operate from early 2028, it would provide up to 100MW of compute; Drax would initially contribute land and access to the national grid via existing connections, and hopes to supply power directly by the early 2030s, subject to regulatory approvals. The proposal comes as ministers plan to reduce Drax’s role and subsidy support amid concerns about its biomass sustainability claims. The project may attract investment and help sustain site jobs, but the article notes wider questions about powering datacentre growth given grid congestion and climate targets.